Napitupulu, Danniel and Asa, M. and Adriana, Ranny (2023) Time And Cost Optimization with The Integration of Building Information Modeling (BIM) 4D and Time Cost Trade-Off Methods (Case Study: Pemali Bridge Project). In: Proceedings of the International Conference on Sustainable Engineering, Infrastructure and Development, ICO-SEID 2022, 23-24 November 2022, Jakarta, Indonesia.
58301.pdf
Download (236kB)
Abstract
Time and cost are highly calculated factors as indicators of project success. The presence of the COVID-19 pandemic has had an impact on the process of completing the Pemali Bridge project, a part of the Brebes-Tegal North Ring Road Project, which has stalled for many years. On this study, time and